HIGH COURT ORDERS GOVERNMENT TO INSPECT THE BORO BORDESHI KHAAL IMMEDIATELY AND FILE INSPECTION REPORTS

Mahbub & Company moved a Writ Petition before the High Court Division of the Supreme Court of Bangladesh on behalf of the land owners surrounding the Boro Bordershi Khaal against the a Real Estate Company seeking protection and restoration of the Boro Bordeshi Khaal, a government-owned natural canal situated at Savar, Dhaka.

The Writ concerned allegations of illegal dredging, sand-filling and encroachment of the canal, which serves as a natural drainage channel for the surrounding locality and connects with the Turag River.

The Petition was brought against the alleged failure of the relevant public authorities to prevent the continued filling and encroachment of the canal. Among other reliefs, the Petition sought cessation of the dredging and earth/sand-filling activities, removal of the filled material and restoration of the canal to its natural depth, width and water-carrying capacity.

At an earlier stage of the proceedings, the Hon’ble High Court had directed the Department of Environment (DoE) to conduct an inquiry and submit a report before the Court. The latest order represents a further step in the Court’s continuing consideration of the environmental and public-safety concerns raised in the Writ.
In its latest order, the Hon’ble Court observed, in substance, that the allegations concerning the use of high-capacity dredgers and the filling and destruction of a natural water channel raise serious questions regarding the protection of the canal and the safety and security of the neighbouring locality and its inhabitants.
The Hon’ble Court considered an immediate factual examination necessary and directed Respondent Nos. 2 and 3, the Ministry of Land and the Ministry of Water Resources, to cause an immediate inspection of the Boro Bordeshi Khaal and to file separate compliance reports enclosing their respective inspection reports within 30 days from the date of the order.

The issues raised in the Writ are particularly significant as the Boro Bordeshi Khaal is recorded as a government-owned waterbody and functions as a primary drainage outlet for Boro Bordeshi Mouza and surrounding areas. The obstruction of its natural flow has caused serious waterlogging and consequential environmental and public-health concerns for neighbouring residents.
The Writ also invoked the statutory protection afforded to natural water reservoirs under Section 6D of the Bangladesh Environment Conservation Act, 1995 and Section 5 of the Playfield, Open Space, Garden and Natural Water Reservoir Conservation Act, 2000.

The matter was represented by Saqeb Mahbub, Partner; Rifat Rahman, Senior Associate; and Md. Parvez Rana, Associate, of Mahbub & Company.

The matter remains pending before the Hon’ble High Court Division.